Home » Products Sourcing » Renewable Energy » Spain’s Acciona Advances 2.4 GW of Energy Storage, 1.8 GW Solar-Wind Hybridization

Spain’s Acciona Advances 2.4 GW of Energy Storage, 1.8 GW Solar-Wind Hybridization

Electric photovoltaic solar panels installed on shopping mall building rooftop

Acciona Energía has just launched its second hybrid wind-solar project in Spain, at Villalba del Rey and Tinajas. A new, 19.7 MWp solar field has been added to a 26 MW wind complex.

Acciona Energía's 19.7 MW solar plant

Acciona Energía’s 19.7 MW solar plant hybridizes the Peralejo wind farm in the municipalities of Villalba del Rey and Tinajas, in Cuenca

Image: Acciona Energia

Madrid-based Acciona Energía has completed its second hybrid renewable generation facility in Spain with the construction of a 19.7 MWp photovoltaic plant at the site of its 26 MW Peralejo wind farm, in the municipalities of Villalba del Rey and Tinajas, in Cuenca. The site will generate 37 GWh of clean electricity per year.

Peralejo is the company’s second hybrid project. Hybridization enables the solar and wind fields to use the same grid connection point.

In January 2024, Acciona commissioned its first hybrid project, the 29.4 MWp solar and 36 MW wind Escepar site in Villalba del Rey. The company also developed the 50 MWp Bolarque photovoltaic plant in Tinajas. Acciona Energía is promoting another hybrid project in Granada, as pv magazine has reported, a 29.54 MW photovoltaic plant will be hybridized with the 30 MW Los Morrones wind farm, launched in 2008 and located in the municipalities of Baza and Zújar.

Acciona Energía has told pv magazine it has 1.8 GW of hybridization projects in the pipeline.

In terms of storage, the portfolio is 2.4 GW, of which 400 MW will be built in the United States.

In 2025, the company plans to build 83 MW of solar generation capacity in the Dominican Republic, at its Pedro Corto project, and 153 MW of in India, with its Juna site. In 2026, Acciona will build 48 MW of solar capacity at the Viscofan project in Spain, 225 MW at two projects in the United States – with another 115 MW to be added in 2027 – and another 100 MW at the Promina project, in Croatia.

This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: editors@pv-magazine.com.

Source from pv magazine

Disclaimer: The information set forth above is provided by pv-magazine.com independently of Alibaba.com. Alibaba.com makes no representation and warranties as to the quality and reliability of the seller and products. Alibaba.com expressly disclaims any liability for breaches pertaining to the copyright of content.

About The Author

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top